Sunday, June 30, 2013

Meanwhile down in Hollywood


With the permit for Wally Remmers's proposed project at 4419-4439 NE Fremont still undergoing "value added revisions" ranging from zoning clarifications to plumbing changes, let's check on another of his family's projects in Hollywood, a neighborhood just south of Beaumont-Wilshire.

Now showing in Hollywood: The Building that Tried to Eat a Neighborhood Landmark. A couple of blocks away, a similarly oversize project offers units from $1,125 to $1,750/month, with a map to neighborhood parking included.
Two buildings went up recently in Hollywood, both big on the number of units and low on amenities. At one of the two, the building across from the library at Northeast 41st and Tillamook, a tour comes with this handy map to all the street parking in the vicinity.

Would-be tenants taking a tour of the new building receive a map to neighborhood parking for vehicles, but nothing on nearby transit or bike facilities.
At the numerous city hearings dedicated to discussing amendments that would put a stop to no-parking buildings of a certain size (like those just opened in Hollywood), many activists in favor of affordable housing and car-free living spoke up in support of this kind of development. They argued that this was precisely the type of housing Portland needed.

Color-coding shows how long to leave a car.
Now the buildings are leasing up. Two-bedroom units at the 41st and Tillamook building run from $1,550 to $1,750, and one-bedrooms are $1,125 to $1,425. Developers enjoyed the support of those activists but the results fall short of expectation—expensive and, for the neighborhood, exploitive.

That is, if Hollywood residents and businesses have no friends or customers.
Here in Beaumont-Wilshire, we hope for better. As the city and developer continue to work on the permit for the troubled, much-delayed development on Northeast Fremont, hopefully they also fix the scale and size of the project and further improve the investment in the neighborhood.

Wednesday, June 12, 2013

We've been here before

Two days short of the city's deadline to submit its record of the permit decision, a required part of the proceedings with the Land Use Board of Appeals, the permit has been withdrawn yet again. For more "strengthening"? Why wait until deadline? All neighbors want is straightforward, transparent process and a final, objective ruling on Wally Remmers's out-of-scale, unmitigated project at 4419-4439 N.E. Fremont. 

No matter. Beaumont-Wilshire Neighbors for Responsible Growth are in it for the long haul, with a belief that the permit, however weak it is, shouldn't have been issued at all. The only silver lining to the delays is that we could get more exposure to our cause and more donations once those 45-foot walls start to rise in the heart of the neighborhood. It is our right to call attention to a development mistake, but these delays prevent us from following the only process with which we can respond. 

After cultivating a hostile environment from the day the developer introducing the project at a neighborhoodwide meeting last summer, and after BWNRG filed its first notice of intent to appeal in early April, Wally Remmers can't be surprised at the seriousness and strength of the pushback. Here it is two months after filing our first notice of intent to appeal, and the city and developer are still working on the permit. It's bad enough that city planning failed us, and now the city keeps throwing a wrench into the path toward resolution.

In happier news, we saw a heartwarming response—and influx to the legal fund: thank you!—at our root-beer social adjacent to the site last weekend. We appreciate all who came out for news about the biggest development in the neighborhood and brainstorming for a better future. If you missed the event, you can contribute online here or through the link at right. As the appeal drags on, costs rise. We are grateful for the support and time people contribute, along with the many professionals who have given us hours of expertise. It's been a long slog getting longer, but we're not alone.

Stay tuned for further developments (ha) as we learn them.


On June 9, members of Beaumont-Wilshire Neighbors for Responsible Growth and concerned citizens gathered to view construction at 4419-4439 NE Fremont, site of a controversial development.

Participants sketch out a better future.

Business owners, neighborhood residents, and more came to get the scoop on Fremont.

Wednesday, June 5, 2013

You know what they say: failing to plan is a plan to fail

In research trips to the Bureau of Development Services, this map on the wall caught my eye. The island of white inside the blue identifies the neighborhoods without plans. No wonder our neighborhood's having problems, such as Wally Remmers' proposed 4-story 50-unit building without parking on Northeast Fremont between 44th and 45th avenues.

With some sites in Beaumont Village still zoned Commercial Storefront, which now we've learned can encompass mondo residential, Beaumont-Wilshire residents have a chance to take a proactive approach to shaping future development.

It may be years yet before we see the revised, long-awaited comprehensive plan from the city. That plan is meant to fix the kind of problems we're seeing with the Remmers project, according to the city's Northeast Liaison Debbie Bischoff. But better not to wait for or depend on that; let's get a plan, man.

Thursday, May 30, 2013

Picture this: scenes from ground level

Some images write their own captions all day long.



















Here are some photos taken during construction of the high-impact project on Northeast Fremont between 44th and 45th avenues. With two cars damaged so far, along with neighbors' fences and trees, as well as crew members running heavy trucks roughshod over Fremont sidewalks and a general disregard for allowed work hours, few friends are being made out there. It shows—among other things—how inappropriately small the site is for the size and ambition of the project, and makes us wonder how the rest of construction will go. If the crew can't take care of the little things, how will they finesse building infrastructure?


Looking south on Northeast 45th, not a lot of room for 36 additional cars.
Looking north, not a lot of extra space either. The street is so narrow that when both sides are parked up, through traffic becomes one-way only. 

Typical rush-hour morning traffic, backed up for three blocks and idling on the crosswalk.
The site's sidewalk closure poses a safety hazard to all.


With bungalows selling for $50,000 over asking and McMansions sprouting in their places, the hammers continue to swing around Beaumont-Wilshire as well as at the contested site of Wally Remmers's low-amenity four-story building on Northeast Fremont. The fact that such an out-of-scale project with outsize impact was given the city's nod makes me recall when, not long ago, the city was accused of being anti-business. Now, with developers exploiting communities across the east side, could the city have swung to the other extreme, to anti-neighbor?

Hopefully this case can be sorted out by the state Land Use Board of Appeals. If all goes to plan and process, the city will produce the record of the permitting decision this time around. When Beaumont-Wilshire Neighbors for Responsible Growth filed its initial notice of intent to appeal, which triggered the LUBA process, it was a day or two before the city's deadline when suddenly the permit was withdrawn for "strengthening."

With the Richmond debacle fresh in our minds, we hope this appeal goes smoothly, that all parties can fulfill their required duties in the time allotted. When I queried Mike Hayakawa, supervising planner at the Bureau of Development Services, about the permissibility of withdrawing the permit to tweak it thus, he said that what they were doing wasn't in the code at all, explaining: "The City of Portland withdrew the building permit decision for the purpose of the legal proceeding at LUBA. Because it is part of the LUBA proceeding, this is not in the city code." How handy that the permit can be fixed while the developer continues to build.

For some background to the no-parking controversy, listen to Rick Michaelson (sp?), testify at City Council last month (fast-forward to 104:55 of Part I), explaining how we came to be in this predicament. Basically, in 1975 as Portlanders saw ever more buildings demolished in the highly dense northwest part of Portland for parking lots, CS-zoned parcels were exempted from parking requirements. With one fell swoop, the city created a neighborhood known for parking hassle and an ongoing migraine for the city's east side. 

It's worth noting that Michaelson, one of the architects of limiting parking lots in Northwest Portland, testified in favor of the parking minimums recently passed by City Council, suggesting they should apply to buildings with as few as 20 units. It's also worth noting that the Northeast Fremont project wouldn't be permitted today as designed. Of course, Beaumont-Wilshire Neighbors for Responsible Growth maintains that it shouldn't have been permitted in the first place, for reasons of parking and many others.

Thursday, May 23, 2013

Let it be LUBA

At a well-attended meeting May 22 (many thanks to those who were able to be there, and for the thoughtful contributions), Beaumont-Wilshire Neighbors for Responsible Growth decided to continue our efforts seeking to influence the outcome of the apartment building project on Fremont between Northeast 44th and 45th avenues. 

We will resubmit a notice of intent to file an appeal with the state Land Use Board of Appeals. The previous notice of intent to appeal filed by our group was stalled by the city and the developer who, instead of producing the record of the permit decision as required by LUBA, withdrew the building permit to "strengthen" it. After the city resubmitted the permit, and LUBA was notified, the appeal process had to begin again.

This pivotal meeting of BWNRG members focused on the realities of the larger impact this apartment building has; not just in the immediate vicinity of the project, but also the broader implications for development in the Beaumont-Wilshire (and more) neighborhoods along Fremont as well as in the other communities in Portland being impacted by large-scale development. We remain committed to maintaining our presence in this important conversation.

Wednesday, May 1, 2013

Does the project have a permit? Depends on who's asking.

With both the city attorney and the developer claiming to have withdrawn the permit for the Northeast Fremont building, it's hard to know who will make what happen next. City staff seem to say that despite the permit being withdrawn for LUBA purposes, it's still in effect at the local level. According to news reports they took the action in order to "strengthen" the permit. Hopefully they come back with amended plans showing a greatly improved building.

Dodging their first deadline to submit the record of the permit to LUBA, the codefendants with this interruption create a longer process, but one that can be restarted if necessary. Despite the setback (ha), Beaumont-Wilshire Neighbors for Responsible Growth hopes for a transparent, cooperative effort that leads to a more successful project and mitigation of outsize impacts.